Hard Rock Construction Co., LLC., crews continue the installation of a new and improved water line system, which is replacing the existing 70+ year-old water lines on the Pontchartrain Park Group A project. Crews are continuing work on Pauline Drive and moving south. A pavement crew has started paving work on Mendez Street between Congress and Piety drives.
We will continue to inform residents ahead of any work that will involve utility disruption and/or impact their parking and access to their street.
This $10M project was designed by Stanley Consultants. As a full depth reconstruction project, work varies block by block but includes:
- Repave asphalt roadway from curb-to-curb;
- Repair damaged sidewalks and driveway aprons;
- Install Americans with Disabilities Act-compliant curb ramps at intersections;
- Replacing /repairing damaged underground water, sewer, and/or drainage lines.
Information about this project was made available at a pre-construction public meeting on September 22, 2020. The presentation can be found here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).