Sewer line work continued in November as six crews from Wallace C. Drennan Inc. facilitated sewer repairs in the Hollygrove, Leonidas Group A project area. Additional work crews focused on putting in the binder and wearing layers of asphalt, which are two of the final steps in roadway restoration.
Scope of work for the $15M infrastructure improvement project may include: replacing/repairing damaged underground water, sewer and/or drainage lines; repairing damaged curbs and gutters; patching the roadway with asphalt; replacing damaged sidewalks and driveway aprons; and installing Americans with Disabilities Act (ADA) compliant curb ramps at intersections.
Waggoner Engineering Inc. is the project designer, and Command Construction Industries, LLC, is the contractor. The project is funded by the Federal Emergency Management Agency (FEMA).
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).