Hard Rock Construction Co., LLC, crews are nearing completion on a $2.2M full depth reconstruction project in the 800 block of St. Ann Street.
The scope of work included:
- Replace damaged underground water, sewer and drainage lines;
- Upgrading underground utilities;
- Repave the roadway;
- Replace damaged sidewalks and driveway aprons;
- Install American with Disabilities Act-compliant curbramps at intersections.
Crews will be onsite for a couple of additional weeks completing final punch list items and performing general clean up duties.
Questions about this project should be directed to 504.658.ROAD (7623) or roadwork@nola.gov.