Wallace C. Drennan, Inc., crews began street excavation and the installation of new water lines this month on the Marleyville-Fontainebleau Group C project. Crews are currently working on State Street between Walmsley and Fontainebleau. We will continue to inform residents ahead of any work that will involve utility disruption and/or impact their parking and access to their street.
This $10.5M project was designed by Schenk, Endom & Flanagan. As a full depth reconstruction project, work varies block by block but includes:
- Repaving asphalt roadway from curb-to-curb;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections;
- Replacing /repairing damaged underground water, sewer, and/or drainage lines.
Information about this project was made available at a pre-construction public meeting on September 10, 2020. The presentation can be found here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).