Latest News

CITY PARK GROUP A MAKES FULL-DEPTH RECONSTRUCTION PROGRESS; BEGINS ROADWAY RECONSTRUCTION

November 11, 2021   |    Category: District A    |   Tagged as: City Park

CITY PARK GROUP A MAKES FULL-DEPTH RECONSTRUCTION PROGRESS; BEGINS ROADWAY RECONSTRUCTION

Fleming Construction crews have completed sewer line point repairs, removal and replacement of exisitng sewer lines, and drainage line improvements on full-depth reconstruction sequences, St. John Court and Allard Boulevard. Crews have now tied in the new waterline to the existing water supply on Allard Boulevard.

WEST END GROUP B CONSTRUCTION NOW UNDER WAY

November 11, 2021   |    Category: District A    |   Tagged as: West End

WEST END GROUP B CONSTRUCTION NOW UNDER WAY

The $7M West End Group B project kicked off construction in June 2021. The contractor Palmisano Construction, LLC is installing sewer and waterlines along 10th  and 12th  streets, which will continue for the next few months. Water main pressure testing is planned throughout the area, and the project team will notify residents 48 before any planned water disruption.

BLACK PEARL/EAST CARROLLTON GROUP A MAKING PROGRESS

November 11, 2021   |    Category: District A    |   Tagged as: Black Pearl / East Carrollton

BLACK PEARL/EAST CARROLLTON GROUP A MAKING PROGRESS

The $11.9M Black Pearl / East Carrollton Group A project, which began construction in August 2020, continues making progress. Contractor Hard Rock Construction Co., LLC is restoring roadways on Maple, Cohn, Birch, Fern and Short streets. Sewer and water line replacement work began in the 200 block of Hillary street and will continue to the 300 block. In the coming months, work will also include sidewalk and Americans with Disabilities Act-compliant ramps throughout the project. The project is expected to be completed in spring 2022, weather permitting.

BLACK PEARL GROUP B CONTINUES MOVING

November 11, 2021   |    Category: District A    |   Tagged as: Black Pearl

BLACK PEARL GROUP B CONTINUES MOVING

The $5.1M Black Pearl Group B project began construction in December 2020. Contractor Infinity Construction is installing sewer, water and drain lines on the block of 100 to 500 Millaudon and the 7700 and 7900 blocks of Dominican, which will continue for the next few months. Water main pressure testing will continue throughout Dominican and Millaudon streets during these installations.

WORK CONTINUES TO PROGRESS THE LAKEVIEW NORTH GROUP C

November 11, 2021   |    Category: District A    |   Tagged as: Lakeview

WORK CONTINUES TO PROGRESS THE LAKEVIEW NORTH GROUP C

Palmisano Construction completed a substantial amount of the project’s waterline work on the Lakeview North Group C infrastructure improvement project during the summer. Crews have completed tie-ins on many streets, including Milne Street and Canal Boulevard. Work is also progressing on sidewalks and driveway aprons. Currently, crews are working on Mouton and Milne Streets, as well as on the areas adjacent to Mount Carmel Academy.

Displaying results 46-50 (of 57)
 |<  <  3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12  >  >| 
November 2021

Posts by month

November 2023 (1)
October 2023 (0)
April 2023 (1)
October 2022 (1)
August 2022 (2)
July 2022 (1)
December 2021 (1)
November 2021 (57)
October 2021 (1)
September 2021 (2)
August 2021 (3)
July 2021 (2)
June 2021 (56)
May 2021 (3)
April 2021 (5)
March 2021 (64)
February 2021 (55)
January 2021 (57)
December 2020 (55)
November 2020 (53)
October 2020 (52)
September 2020 (44)
August 2020 (40)
July 2020 (38)
June 2020 (38)
May 2020 (34)
April 2020 (30)
March 2020 (29)
February 2020 (30)
January 2020 (23)
November 2019 (24)
October 2019 (21)
September 2019 (22)
August 2019 (18)
July 2019 (18)
June 2019 (23)
May 2019 (23)
April 2019 (23)
March 2019 (23)
February 2019 (27)
January 2019 (27)
December 2018 (26)
November 2018 (26)
October 2018 (26)
September 2018 (27)
August 2018 (27)
July 2018 (26)
June 2018 (29)
May 2018 (21)
April 2018 (20)
March 2018 (18)
February 2018 (20)
January 2018 (20)
November 2017 (17)
October 2017 (15)
September 2017 (14)
August 2017 (13)
July 2017 (18)
June 2017 (16)
May 2017 (14)
April 2017 (15)
March 2017 (17)

Posts by category

Citywide
District A
District B
District C
District D
District E

Posts by project

Algiers
Aubry St
Audubon
Bayou St. John, Fairgrounds, Seventh Ward
Belleville St
Berkeley Dr
bike lanes
Black Pearl
Black Pearl / East Carrollton
Blue & Green Corridors
Bocage
Bourbon
Breakwater Drive
Broad St
Broadmoor
Bullard Ave
Bywater-Marigny
Canal Blvd
Canal St
Central City
Cherokee St
City Park
Community Meeting
Conti
Convention Center Blvd
Curran Blvd
Desire
Desire/Gordon Plaza
East Riverside/Garden District/Irish Channel/St. Thomas
Filmore
Fleur de Lis
Fontainebleau
Fountainebleau
French Quarter
Freret
Gentilly Resilience District
Gentilly Terrace
Gravier St
Green Infrastructure
Hagan Lafitte
Henry Clay
Hollygrove
Hollygrove, Leonidas
Infrastructure Industry Day
Jackson Ave
Joe Brown Park Bridge
Lacour Monique and Eton St.
Lafitte Corridor Greenway
LAKE TERRACE AND OAKS
Lake Vista
Lakeshore
Lakeview
Lakewood
Little Woods
Lower Ninth Ward
Magazine
Magnolia Bridge
Maintenance Improvements
Marconi
Marleyville-Fontainebleau
Maurepas St and Mystery St
Max Pave II
Message from the Mayor
Michoud Blvd
Mid City
Milneburg
Mirabeau Water Garden
Moving New Orleans Bikes
Navarre
New Aurora
New Orleans East
North Claiborne
Oak Park
Octavia Street
Old Spanish Trail
Pilotland
Pines Village
Pittari St.
Plum Orchard / West Lake Forest
Pontchartrain Park
Pontilly
Read Blvd
Resilience
S Galvez
Safe Routes to School
Saratoga Square
St Claude
St Louis Canal
St. Ann
St. Bernard
St. Charles
St. Roch
Streetscape
SWB
Taft Place
Traffic Advisory
Treme-Lafitte
Viavant-Lake Catherine
Village de L’Est
West Bank
West End
Wisner Bridge
Wright Rd
Youth Study Streets


Looking for work?

The City of New Orleans and the Sewerage & Water Board are hiring.

Find jobs with the City

Find jobs with S&WB

Connect to First Source


Contact us

You can contact us directly at ose@nola.gov
or by phone at (504) 658-7623.