Boh Bros Construction Company, LLC crews are performing sewer line and waterline work along 3600 Livingston, 2800 Hamilton and 3400 Camphor streets. Roadway restoration will follow the completion of successful waterline tie-ins throughout October for these areas. Crews are currently completing roadway restoration along 3600 Mistletoe Street.
If residents notice catch basins obstructed with construction materials, please contact RoadworkNOLA at 504.658.ROAD (7623).
We will continue to inform residents ahead of any work that will involve utility disruption and / or impact their parking and access to their street and driveways.
This $20.3M project was designed by Waggoner Engineering and the scope of work varies block by block but includes:
- Replacement of roadways;
- Repave the roadway;
- Replacement of sidewalks and driveway aprons;
- Install Americans with Disabilities Act (ADA)-compliant curb ramps at intersection; and
- Replacement and / or upgrades to underground water, sewer, and / or drainage utilities
The project began in July 2021 and is expected to be completed in winter 2022, weather permitting.
Information about this project was made available at a June 2021, public pre-construction meeting. The presentation can be found here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).