More than 70% of the waterline work has been completed on the Little Woods Group A project. While there are some remaining blocks, paving is scheduled to be completed on Wave, Duane, Branch, Sandy Cove, Pebble, Jon Lee, Scottwood and Alabama streets in October. Sidewalks, driveways and curbs in both Kingswood and Lake Carmel subdivisions are also expected to be complete in November.
Any residents that require reasonable accommodations on the site are encouraged to call the Roadwork NOLA hotline. Residents will continue to be informed ahead of any work that will involve utility disruption and / or impact their parking and access to their streets.
The scope of this $14M patch, mill, overlay and incidental road repairs project varies by block but includes:
- Repaving the asphalt roadway from curb-to-curb;
- Patching the roadway with asphalt or concrete;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replacing / repairing damaged underground water, sewer, and / or drainage lines.
Details of this project were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).