The $10.1M Milneburg Group B Full Reconstruction project started work in December of 2020 and is expected to complete construction in winter 2021. This project is completed in parallel with the Milneburg Group A project and addresses the roadway infrastructure in key areas of the neighborhood where full reconstruction is required, specifically Mandeville Street and Vienna Street near Pierre A Capdau at Avery Alexander Elementary School. High water levels and heavy rain contributed significant delays to closed circuit television sewer and drain line explorations that are necessary for performing repair and replacement. Waterline work on this project is complete. Workers will continue to replace driveway aprons along Spain, New York and Marigny streets.
This project was designed by Design Engineering, Inc. and is being constructed by Hard Rock Construction, LLC. Click here to view a map of the project. The scope of work includes:
- Full Reconstruction: Repairing sewage, water, and drainage line, rebuild the street entirely, and repair sidewalks and curbs:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
The City of New Orleans held a public community meeting in November 2020 to discuss anticipated impacts to the community. View a copy of the presentation here. To be added to the project contact list and track our progress, visit roadwork.nola.gov