City of New Orleans contractor The Three C's Properties, Inc. continues to work ahead of schedule on the Lakeshore Group A project. Last month, crews completed roadway repairs and curbs on Emerald, Gem, General Haig and Turquoise streets. The project is currently 60 percent complete. The City is now awaiting approval from FEMA on additional scopes of work that will improve drainage in the area.
This $1.1 million Incidental Road Repair project includes the following scope of work:
- Patching the roadway with asphalt;
- Replacing damaged portions of concrete with new, level concrete;
- Repairing damaged curbs and gutters;
- Repairing damaged sidewalks and driveway aprons;
- Installing ADA-compliant curb ramps at intersection; and
- Replacing/repairing damaged, underground water and drainage lines.
The City hosted a pre-construction public meeting to discuss the construction sequencing and anticipated impacts. View a copy of the public meeting presentation here.