Hard Rock Construction crews are continuing work on a $2.2M full depth reconstruction project in the 800 block of St. Ann Street. The contractor has fully reconstructed the roadway, and it has reopened it to pedestrian traffic only while sidewalks remain closed for repairs.
The intersection of Dauphine and St. Ann streets reopened to vehicular traffic on October 19. The entire project is scheduled to be completed in October 2020, weather permitting. To date, crews have installed a new, upsized 24-inch drain line, new water line, new sewer line, and restored the roadway.
Questions about this project should be directed to 504.658.ROAD (7623) or roadwork@nola.gov.