Command Construction, LLC crews continued repaving all areas during the month of September on the Little Woods Group A project. With a large percentage of the open areas addressed, crews are expected to begin on roadway operations on other parts of the project in October.
Crews will continue working on water line tie-ins, sidewalk restoration and driveway aprons throughout the project in an effort to get back on schedule. Residents will be notified of work that will impact their access and/or cause disruption to their utilities.
The scope of this $14M Patch, Mill, Overlay and Incidental Road Repair project varies by block but includes:
- Repaving the asphalt roadway from curb-to-curb;
- Patching the roadway with asphalt or concrete;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replacing / repairing damaged underground water, sewer, and/or drainage lines.
Details of this project were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).