Beverly Construction crews have completed 80 percent of the water line and roadway restoration work on the Read Boulevard East Group B project. Tie-ins were successfully completed throughout the project through September. Crews have also completed roadway restoration in many areas, including Sierra Madre Drive. Crews will continue work on the remaining water line work and sidewalk operations through the month of October.
Residents will continue to be notified of work that will impact their access and/or cause disruption to their utilities.
The scope of this $3.6M Patch, Mill, Overlay and Incidental Road Repair project varies by block but includes:
- Repaving the asphalt roadway from curb-to-curb;
- Patching the roadway with asphalt or concrete;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replacing / repairing damaged underground water, sewer, and/or drainage lines.
Details of this project were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).