Work continues on the full reconstruction of the 800 and 900 blocks of Taft Place.
The scope of work for the $2.3M FEMA-funded project includes repairing sewer, water, and drainage lines; rebuilding the street entirely; repairing sidewalks and curbs; and installing Americans with Disabilities Act (ADA) compliant curb ramps.
The project, designed by ECM Consultants, Inc. and awarded to Beverly Construction, is scheduled to be complete by the end of 2019, weather permitting.
View a copy of the presentation given at the June public meeting here. To be added to the project contact list, and to track our progress, visit Roadwork.nola.gov.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).