The St. Claude Group A project was designed by Rahman and Associates, Inc. and is being built by Hard Rock Construction Company, LLC. There is an estimated $1M in added scope on the $3.8M project, which is scheduled to be complete in early 2020.
Work is currently occurring on St. Ferdinand and Alvar streets. Waterline work will start on N. Roman and Independence streets in the coming weeks. Drainage upgrades are planned for Bartholomew, Independence and Derbigny streets.
The scope varies by block, but includes the following types of work:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
Learn more about the project’s construction sequencing and anticipated impacts by viewing a copy of the public meeting presentation here.