Boh Bros Construction Co, LLC crews, in close collaboration with Sewerage and Water Board of New Orleans, began preparations for tying in the newly installed water lines on the Lake Terrace and Oaks Group D project in September. Crews are currently working on Oriole Street but will continue to inform residents ahead of any work that will involve utility disruption and/or impact their parking and access to their street.
This $5.8M project was designed by Mott MacDonald. As a full depth reconstruction project, work varies block by block but includes:
- Replace damaged underground water, sewer and drainage lines;
- Repave the roadway;
- Replace damaged sidewalks and driveway aprons; and
- Install Americans with Disabilities Act-compliant curb ramps at intersections.
Information about this project was made available at a pre-construction public meeting on May 20, 2020. The presentation can be found here.