Boh Bros crews, in close collaboration with Sewerage and Water Board of New Orleans, have begun water line operations on the Audubon Group A project. Water line installations have been completed on Arabella, Pitts and Joseph streets. In addition to water line work, crews continue to form and pour ADA-compliant intersections. They recently completed concrete pours on Octavia and Arabella streets.
Residents will continue to be informed ahead of any work that will involve utility disruption and/or impact their parking and access to their streets.
This $7.3M project was designed by All South Consulting Engineers, LLC. The scope of work varies block by block but includes the following:
- Repave the asphalt roadway from curb-to-curb;
- Patch the roadway with asphalt or concrete;
- Repair damaged sidewalks and driveway aprons;
- Install Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replace / repair damaged underground water, sewer, and/or drainage lines.
Information about this project was made available at a pre-construction public meeting on May 21, 2020. The presentation can be found here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).