The $7M West Bank Group B project was designed by Buchart Horn, Inc. and began construction in March 2020. Contractor Fleming Construction continues its focus on Elizardi, Lawrence, Murl, Odeon, Pace, and Shallett streets, as well as Westbend Parkway.
Click here to view a map of the planned work on the project. The scope of work varies by block and includes the following:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
The City of New Orleans held a public meeting about the project in March 2020 to discuss anticipated impacts to the community. View a copy of the meeting presentation here. To be added to the project contact list and track our progress, visit roadwork.nola.gov.