Roubion Shoring & Construction crews completed sidewalk pours and placed Americans with Disabilities Act-compliant ramps on the Gentilly Terrace Group A project this month. Crews are 85 percent complete in the first phase of construction (northern portions of the project bounded by Gentilly Boulevard and Filmore Avenue) and plan to start the second phase (southern portions of area bounded by Gentilly Boulevard and Interstate-610) in June.
This $2.2 million project includes the following types of work:
- Patch Mill / Overlay: Repaving the asphalt roadway from curb to curb and repairing damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
Details of the construction sequencing and timeline were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work in the area, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).