July 27, 2017 | Category: District E | Tagged as: New Orleans East
The City is planning to use funds approved by voters during the 2016 bond sale to re-pave several high traffic roadways in New Orleans East this summer.
July 27, 2017 | Category: District E | Tagged as: Joe Brown Park Bridge
Boh Bros. Construction Co., LLC has completed installing the bridge base over the North Lagoon at Joe W. Brown Memorial Park. The pre-fabricated bridge was delivered on July 25.
July 27, 2017 | Category: District E | Tagged as: Michoud Blvd
The long-awaited Michoud Blvd. reconstruction project is approximately 10 percent complete. Crews mobilized to the site in early June and are currently installing a new bus turn around on the Dwyer Rd. neutral ground and are installing the sewer force main in the Michoud Blvd. neutral ground.
July 27, 2017 | Category: District D | Tagged as: Youth Study Streets
Dieudonne Enterprises, LLC construction crews are now 45 percent complete with the Youth Study Center Streets construction project in the Pilotland neighborhood.
July 27, 2017 | Category: District C | Tagged as: French Quarter
The City of New Orleans’ construction contractor, Hard Rock Construction, LLC recently began installing sidewalks along the 800 - 1300 blocks of Decatur St. as part of the French Quarter Sidewalk Improvement Program, Phase 2.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at ose@nola.gov or by phone at (504) 658-7623.
This website uses cookies to ensure you get the best experience. By using our website, you agree to our cookie policy.
OK