January 31, 2020 | Category: District D | Tagged as: Canal Blvd
Crews from Palmisano Construction continue installation of drainage and sewer lines on northbound Canal between Robert E. Lee Boulevard. and Amethyst Street.
January 31, 2020 | Category: District E | Tagged as: Pines Village
The City of New Orleans, Department of Public Works (DPW), in conjunction with the Sewerage and Water Board of New Orleans, began road repairs in the New Orleans East area on January 21.
January 31, 2020 | Category: District E
The City of New Orleans, Department of Public Works (DPW), in conjunction with the Sewerage and Water Board of New Orleans, began road repairs this month in the Read Boulevard East area.
January 31, 2020 | Category: District E | Tagged as: Village de L’Est
Construction is progressing on the second project in the Village De L’Est area. Crews are working on sidewalks and driveways on Endeavors Court and Expedition Drive. Roadway pavement continues on Beaucaire Street and Point Coupe Place. The project is anticipated to be completed in early fall 2020.
January 31, 2020 | Category: District E | Tagged as: Lower Ninth Ward
Wallace C. Drennan crews continue work on the Lower Ninth Ward Northwest Group B project. Crews are currently installing water lines on Reynes Street from N. Derbigny Street to Tonti Street. Residents will continue to be notified ahead of any work that will impact their access and utilities.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at ose@nola.gov or by phone at (504) 658-7623.
This website uses cookies to ensure you get the best experience. By using our website, you agree to our cookie policy.