Latest News

NAVARRE GROUP A NEARING COMPLETION

November 11, 2021   |    Category: District A    |   Tagged as: Navarre

NAVARRE GROUP A NEARING COMPLETION

The $9.1M Navarre Group A project, which began construction in February 2020, continues to move forward as scheduled. Contractor Hard Rock Construction Co., LLC has completed waterline tie-ins and drainage work ahead of asphalt installation on the 5500 and 5600 blocks of Catina Street. Crews are moving to General Diaz Street following the completion of paving on Catina Street in early October. Significant progress on the project was made during the summer of 2021 and work is nearing 90% completion – the project is expected to finalize in fall 2021, weather permitting. Coordination is ongoing with residents to ensure that site clean-up and final, punch list items are addressed by the contractor before the project is completed.

CONCRETE WORK, ROADWAY RESTORATION UNDERWAY IN NAVARRE GROUP A PROJECT

June 4, 2021   |    Category: District A    |   Tagged as: Navarre

CONCRETE WORK, ROADWAY RESTORATION UNDERWAY IN NAVARRE GROUP A PROJECT

Concrete crews began forming curbs and gutter bottoms on South Park Place, and additional crews also continued working on sidewalks and driveway aprons on Central Park, South Park and Conscino streets. The binder layer of asphalt has been installed on South Park Place, Binder is one of the final layers of asphalt in the roadway restoration process.  

 

ROADWAY RESTORATION CONTINUES IN NAVARRE GROUP A PROJECT

March 31, 2021   |    Category: District A    |   Tagged as: Navarre

ROADWAY RESTORATION CONTINUES IN NAVARRE GROUP A PROJECT

Hard Rock Construction Co., LLC crews began removing the roadway surface on General Diaz between Homedale and Pontalba this month, and patched areas along Vicksburg and Homedale streets. Crews replaced the faulty hydrant at Louque and General Diaz streets, and applied the binder layer of asphalt to portions of East Park and Central Park places. The roadway base on South Park Place was removed and will be regraded. A density test will be performed before the binder layer is reinstalled. Binder is one of the final layers of pavement restoration and it is drivable.

ROADWAY RESTORATION CONTINUES IN NAVARRE GROUP A PROJECT

March 2, 2021   |    Category: District A    |   Tagged as: Navarre

ROADWAY RESTORATION CONTINUES IN NAVARRE GROUP A PROJECT

Hard Rock Construction Co., LLC crews began installing an asphalt binder course (between the foundation and upper layer) on East Park, Central Park and General Diaz streets this month, as well as placing new concrete curb and gutter bottoms. Excavations began on the roadway patches on Homedale and Vicksburg streets, West End Boulevard and Ada Place, along with the asphalt failures on South Park Place. Roadway milling is being scheduled.

ROADWAY EXCAVATIONS AND RESTORATION TAKING PLACE IN NAVARRE GROUP A PROJECT

January 27, 2021   |    Category: District A    |   Tagged as: Navarre

ROADWAY EXCAVATIONS AND RESTORATION TAKING PLACE IN NAVARRE GROUP A PROJECT

In January, crews from Hard Rock Construction Co., LLC began installing new concrete curbs and gutters along Central Park and East Park Place, and the wearing course  (one of the final layers of roadway restoration) of asphalt was laid on North Park and Middle Park Place. Overall the project is more than 70 percent complete.   

Displaying results 1-5 (of 16)
 |<  < 1 - 2 - 3 - 4  >  >| 

Posts by month

November 2023 (1)
October 2023 (0)
April 2023 (1)
October 2022 (1)
August 2022 (2)
July 2022 (1)
December 2021 (1)
November 2021 (57)
October 2021 (1)
September 2021 (2)
August 2021 (3)
July 2021 (2)
June 2021 (56)
May 2021 (3)
April 2021 (5)
March 2021 (64)
February 2021 (55)
January 2021 (57)
December 2020 (55)
November 2020 (53)
October 2020 (52)
September 2020 (44)
August 2020 (40)
July 2020 (38)
June 2020 (38)
May 2020 (34)
April 2020 (30)
March 2020 (29)
February 2020 (30)
January 2020 (23)
November 2019 (24)
October 2019 (21)
September 2019 (22)
August 2019 (18)
July 2019 (18)
June 2019 (23)
May 2019 (23)
April 2019 (23)
March 2019 (23)
February 2019 (27)
January 2019 (27)
December 2018 (26)
November 2018 (26)
October 2018 (26)
September 2018 (27)
August 2018 (27)
July 2018 (26)
June 2018 (29)
May 2018 (21)
April 2018 (20)
March 2018 (18)
February 2018 (20)
January 2018 (20)
November 2017 (17)
October 2017 (15)
September 2017 (14)
August 2017 (13)
July 2017 (18)
June 2017 (16)
May 2017 (14)
April 2017 (15)
March 2017 (17)

Posts by category

Citywide
District A
District B
District C
District D
District E

Posts by project

Algiers
Aubry St
Audubon
Bayou St. John, Fairgrounds, Seventh Ward
Belleville St
Berkeley Dr
bike lanes
Black Pearl
Black Pearl / East Carrollton
Blue & Green Corridors
Bocage
Bourbon
Breakwater Drive
Broad St
Broadmoor
Bullard Ave
Bywater-Marigny
Canal Blvd
Canal St
Central City
Cherokee St
City Park
Community Meeting
Conti
Convention Center Blvd
Curran Blvd
Desire
Desire/Gordon Plaza
East Riverside/Garden District/Irish Channel/St. Thomas
Filmore
Fleur de Lis
Fontainebleau
Fountainebleau
French Quarter
Freret
Gentilly Resilience District
Gentilly Terrace
Gravier St
Green Infrastructure
Hagan Lafitte
Henry Clay
Hollygrove
Hollygrove, Leonidas
Infrastructure Industry Day
Jackson Ave
Joe Brown Park Bridge
Lacour Monique and Eton St.
Lafitte Corridor Greenway
LAKE TERRACE AND OAKS
Lake Vista
Lakeshore
Lakeview
Lakewood
Little Woods
Lower Ninth Ward
Magazine
Magnolia Bridge
Maintenance Improvements
Marconi
Marleyville-Fontainebleau
Maurepas St and Mystery St
Max Pave II
Message from the Mayor
Michoud Blvd
Mid City
Milneburg
Mirabeau Water Garden
Moving New Orleans Bikes
Navarre
New Aurora
New Orleans East
North Claiborne
Oak Park
Octavia Street
Old Spanish Trail
Pilotland
Pines Village
Pittari St.
Plum Orchard / West Lake Forest
Pontchartrain Park
Pontilly
Read Blvd
Resilience
S Galvez
Safe Routes to School
Saratoga Square
St Claude
St Louis Canal
St. Ann
St. Bernard
St. Charles
St. Roch
Streetscape
SWB
Taft Place
Traffic Advisory
Treme-Lafitte
Viavant-Lake Catherine
Village de L’Est
West Bank
West End
Wisner Bridge
Wright Rd
Youth Study Streets


Looking for work?

The City of New Orleans and the Sewerage & Water Board are hiring.

Find jobs with the City

Find jobs with S&WB

Connect to First Source


Contact us

You can contact us directly at roadwork@nola.gov
or by phone at (504) 658-ROAD (7623).