Latest News

HOLLYGROVE, LEONIDAS GROUP A CONTRACTOR INCREASING PACE OF CONSTRUCTION

November 11, 2021   |    Category: District A    |   Tagged as: Hollygrove, Leonidas

HOLLYGROVE, LEONIDAS GROUP A CONTRACTOR INCREASING PACE OF CONSTRUCTION

The $15.3M Hollygrove, Leonidas Group A project began construction in April 2020. Contractor Wallace C. Drennan, Inc. is replacing and repairing sewer lines along the project and will move into deeper sewer repairs as water levels subside. Some sewer line work has been halted on this project due to high river levels and heavy rainfall, which limited the ability to certify sewer repairs. Work is resuming in those areas as the river levels decrease. Crews have continued to work on roadway removal sitewide and asphalt repaving along Hollygrove Street.

PAVEMENT RESTORATION, SEWER LINE REPAIRS CONTINUE IN HOLLYGROVE, LEONIDAS GROUP A

June 4, 2021   |    Category: District A    |   Tagged as: Hollygrove, Leonidas

PAVEMENT RESTORATION, SEWER LINE REPAIRS CONTINUE IN HOLLYGROVE, LEONIDAS GROUP A

Roadway removal and grading began in the 700 block of Dublin, the 1100, 2500 and 2700 blocks of Joliet Street, and the 8900 block of Nelson Street this month.  Crews also started creating the forms and prepping for concrete pours in the 3700 block of Live Oak and the 9500 block of Palm streets. Sewer line point repairs continued along Palm and Hollygrove streets, and the binder layer of asphalt was scheduled for installation in the 2600-2700 blocks of Mistletoe Street. Binder is one of the final layers of asphalt in roadway restoration. 

PAVEMENT RESTORATION CONTINUES IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

March 31, 2021   |    Category: District A    |   Tagged as: Hollygrove, Leonidas

PAVEMENT RESTORATION CONTINUES IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

In March, Drennan Construction, LLC installed asphalt in the 2400 and 2500 blocks of Mistletoe Street and started the repaving process in the 1900 block of Dublin Street. Crews also began pouring new concrete sidewalks and driveway aprons throughout the project footprint. Roadway excavation began in the 8900 blocks of Apple and Nelson and was followed with installation of the binder layer of asphalt. The binder is one of the final layers of pavement restoration and residents are able to drive on it.

SEWER REPAIRS, PAVEMENT RESTORATION CONTINUE IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

March 2, 2021   |    Category: District A    |   Tagged as: Hollygrove, Leonidas

SEWER REPAIRS, PAVEMENT RESTORATION CONTINUE IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

The Hollygrove, Leonidas Group A project continues to make progress. Additional sewer line issues were identified, and crews began making those repairs in early February. In addition to laying new wearing course (upper layer in the roadway) layers of asphalt throughout the project area, Drennan Construction Industries, LLC completed the intersection work required at Birch and Cambronne streets. Excavation operations continued, along with forming new Americans with Disabilities Act (ADA)-compliant curb ramps at intersections.

SEWER REPAIRS, PAVEMENT RESTORATION UNDERWAY IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

January 27, 2021   |    Category: District A    |   Tagged as: Hollygrove, Leonidas

SEWER REPAIRS, PAVEMENT RESTORATION UNDERWAY IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

The Hollygrove, Leonidas Group A project is making significant progress. Sewer line work is substantially complete, and pavement restoration work activity has increased throughout the project area. Crews began laying the bunder layer of asphalt (one of the last layers of asphalt installed for roadway restoration) in the following blocks in January:  2600 General Ogden; 8900 Belfast; 8200 and 8600 Zimpel; 900 - 1100 Dante; 800, 1200, and 1500  Cambronne; 1300 and 1700  Monroe; 8900  Jeannette; 8500 Birch; 8800  Green; 1800 Hamilton; and 2500 Joliet.

Displaying results 1-5 (of 15)
 |<  < 1 - 2 - 3  >  >| 

Posts by month

November 2023 (1)
October 2023 (0)
April 2023 (1)
October 2022 (1)
August 2022 (2)
July 2022 (1)
December 2021 (1)
November 2021 (57)
October 2021 (1)
September 2021 (2)
August 2021 (3)
July 2021 (2)
June 2021 (56)
May 2021 (3)
April 2021 (5)
March 2021 (64)
February 2021 (55)
January 2021 (57)
December 2020 (55)
November 2020 (53)
October 2020 (52)
September 2020 (44)
August 2020 (40)
July 2020 (38)
June 2020 (38)
May 2020 (34)
April 2020 (30)
March 2020 (29)
February 2020 (30)
January 2020 (23)
November 2019 (24)
October 2019 (21)
September 2019 (22)
August 2019 (18)
July 2019 (18)
June 2019 (23)
May 2019 (23)
April 2019 (23)
March 2019 (23)
February 2019 (27)
January 2019 (27)
December 2018 (26)
November 2018 (26)
October 2018 (26)
September 2018 (27)
August 2018 (27)
July 2018 (26)
June 2018 (29)
May 2018 (21)
April 2018 (20)
March 2018 (18)
February 2018 (20)
January 2018 (20)
November 2017 (17)
October 2017 (15)
September 2017 (14)
August 2017 (13)
July 2017 (18)
June 2017 (16)
May 2017 (14)
April 2017 (15)
March 2017 (17)

Posts by category

Citywide
District A
District B
District C
District D
District E

Posts by project

Algiers
Aubry St
Audubon
Bayou St. John, Fairgrounds, Seventh Ward
Belleville St
Berkeley Dr
bike lanes
Black Pearl
Black Pearl / East Carrollton
Blue & Green Corridors
Bocage
Bourbon
Breakwater Drive
Broad St
Broadmoor
Bullard Ave
Bywater-Marigny
Canal Blvd
Canal St
Central City
Cherokee St
City Park
Community Meeting
Conti
Convention Center Blvd
Curran Blvd
Desire
Desire/Gordon Plaza
East Riverside/Garden District/Irish Channel/St. Thomas
Filmore
Fleur de Lis
Fontainebleau
Fountainebleau
French Quarter
Freret
Gentilly Resilience District
Gentilly Terrace
Gravier St
Green Infrastructure
Hagan Lafitte
Henry Clay
Hollygrove
Hollygrove, Leonidas
Infrastructure Industry Day
Jackson Ave
Joe Brown Park Bridge
Lacour Monique and Eton St.
Lafitte Corridor Greenway
LAKE TERRACE AND OAKS
Lake Vista
Lakeshore
Lakeview
Lakewood
Little Woods
Lower Ninth Ward
Magazine
Magnolia Bridge
Maintenance Improvements
Marconi
Marleyville-Fontainebleau
Maurepas St and Mystery St
Max Pave II
Message from the Mayor
Michoud Blvd
Mid City
Milneburg
Mirabeau Water Garden
Moving New Orleans Bikes
Navarre
New Aurora
New Orleans East
North Claiborne
Oak Park
Octavia Street
Old Spanish Trail
Pilotland
Pines Village
Pittari St.
Plum Orchard / West Lake Forest
Pontchartrain Park
Pontilly
Read Blvd
Resilience
S Galvez
Safe Routes to School
Saratoga Square
St Claude
St Louis Canal
St. Ann
St. Bernard
St. Charles
St. Roch
Streetscape
SWB
Taft Place
Traffic Advisory
Treme-Lafitte
Viavant-Lake Catherine
Village de L’Est
West Bank
West End
Wisner Bridge
Wright Rd
Youth Study Streets


Looking for work?

The City of New Orleans and the Sewerage & Water Board are hiring.

Find jobs with the City

Find jobs with S&WB

Connect to First Source


Contact us

You can contact us directly at roadwork@nola.gov
or by phone at (504) 658-ROAD (7623).