January 25, 2018 | Category: District E | Tagged as: Lower Ninth Ward
The second of several planned FEMA-funded construction projects, which will help improve road conditions in the Lower Ninth Ward neighborhood, is now under construction. The Lower Ninth Ward Northeast Group A, was designed by Neel - Schaffer, Inc. and awarded to Beverly Construction LLC for $3.4M.
The Department of Public Works’ construction contractor, Fleming Construction Co., LLC, is progressing well on the $4.7M Lower Ninth Ward Northwest Group A, which began in December 2017.
January 25, 2018 | Category: District E | Tagged as: Bullard Ave
The Department of Public Works’ construction contractor, Roubion Roads and Streets, LLC. is approximately 50 percent complete with replacing damaged concrete panels on Bullard Avenue between Hayne Boulevard and Chef Menteur Highway.
January 25, 2018 | Category: District E | Tagged as: Curran Blvd
The Department of Public Works’ construction contractor, Barriere Construction, LLC., is approximately 25 percent complete with the repaving Curran Boulevard project. This project is scheduled to be completed in the spring.
January 25, 2018 | Category: District E | Tagged as: Read Blvd
Command Construction Industries, LLC crews are currently moving traffic control signs and barrels into the neighborhood and beginning to mark out future excavation sites. This is the first of two construction projects planned for the Read Boulevard West neighborhood. Bounded by Dwyer Road, Read Boulevard, Flake Avenue and Chef Menteur Highway.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at ose@nola.gov or by phone at (504) 658-7623.
This website uses cookies to ensure you get the best experience. By using our website, you agree to our cookie policy.