Latest News

Clean Up NOLA: Adopt-A-Catch Basin: Cleaning Days 2018

September 21, 2018   |    Category: Citywide

Clean Up NOLA: Adopt-A-Catch Basin: Cleaning Days 2018

In an effort to engage residents in the Clean Up NOLA initiative, the Mayor’s Neighborhood Engagement Office will host a City-wide Catch Basin Cleaning Training followed by a series of Catch Basin Cleaning Days in each Council District.

CREWS CONTINUE TO WORK WEEKENDS, KEEPING THE LOWER NINTH WARD NORTHEAST GROUP A PROJECT ON SCHEDULE

September 21, 2018   |    Category: District E    |   Tagged as: Lower Ninth Ward

CREWS CONTINUE TO WORK WEEKENDS, KEEPING THE LOWER NINTH WARD NORTHEAST GROUP A PROJECT ON SCHEDULE

City of New Orleans contractor Beverly Construction LLC continues to work on Saturdays on the Lower Ninth Ward Northeast Group A project to make up for time lost during the Labor Day holiday and inclement weather days.

1600 BLOCK OF CAFFIN AVENUE, PART OF THE LOWER NINTH WARD NORTHWEST PROJECT, REOPENS

September 21, 2018   |    Category: District E    |   Tagged as: Lower Ninth Ward

1600 BLOCK OF CAFFIN AVENUE, PART OF THE LOWER NINTH WARD NORTHWEST PROJECT, REOPENS

As progress continues on the $4.8M Lower Ninth Ward Northwest Group A project, the Department of Public Works’ construction contractor, Fleming Construction Co., LLC, removed barricades on several streets including the 1600 block of Caffin Avenue.

NEW ORLEANS EAST BRIDGES CONTRACT TO RE-BID

September 21, 2018   |    Category: District E    |   Tagged as: New Orleans East

NEW ORLEANS EAST BRIDGES CONTRACT TO RE-BID

The City’s procurement office has deemed the two responses for the contract that would rehabilitate several closed bridges in New Orleans East to be non-responsive. As a result, the project will be re-bid.

ROADWAY REPAVEMENT IN JOE W BROWN MEMORIAL PARK CURRENTLY 95 PERCENT COMPLETE

September 21, 2018   |    Category: District E    |   Tagged as: Joe Brown Park Bridge

ROADWAY REPAVEMENT IN JOE W BROWN MEMORIAL PARK CURRENTLY 95 PERCENT COMPLETE

City’s construction contractor, Barriere Construction Co., LLC has currently completed 95 percent of the roadway repavement in Joe W. Brown Memorial Park. The $1.2M construction project is scheduled to be completed at the end of September.

Displaying results 1-5 (of 27)
 |<  < 1 - 2 - 3 - 4 - 5 - 6  >  >| 
September 2018

Posts by month

November 2023 (1)
October 2023 (0)
April 2023 (1)
October 2022 (1)
August 2022 (2)
July 2022 (1)
December 2021 (1)
November 2021 (57)
October 2021 (1)
September 2021 (2)
August 2021 (3)
July 2021 (2)
June 2021 (56)
May 2021 (3)
April 2021 (5)
March 2021 (64)
February 2021 (55)
January 2021 (57)
December 2020 (55)
November 2020 (53)
October 2020 (52)
September 2020 (44)
August 2020 (40)
July 2020 (38)
June 2020 (38)
May 2020 (34)
April 2020 (30)
March 2020 (29)
February 2020 (30)
January 2020 (23)
November 2019 (24)
October 2019 (21)
September 2019 (22)
August 2019 (18)
July 2019 (18)
June 2019 (23)
May 2019 (23)
April 2019 (23)
March 2019 (23)
February 2019 (27)
January 2019 (27)
December 2018 (26)
November 2018 (26)
October 2018 (26)
September 2018 (27)
August 2018 (27)
July 2018 (26)
June 2018 (29)
May 2018 (21)
April 2018 (20)
March 2018 (18)
February 2018 (20)
January 2018 (20)
November 2017 (17)
October 2017 (15)
September 2017 (14)
August 2017 (13)
July 2017 (18)
June 2017 (16)
May 2017 (14)
April 2017 (15)
March 2017 (17)

Posts by category

Citywide
District A
District B
District C
District D
District E

Posts by project

Algiers
Aubry St
Audubon
Bayou St. John, Fairgrounds, Seventh Ward
Belleville St
Berkeley Dr
bike lanes
Black Pearl
Black Pearl / East Carrollton
Blue & Green Corridors
Bocage
Bourbon
Breakwater Drive
Broad St
Broadmoor
Bullard Ave
Bywater-Marigny
Canal Blvd
Canal St
Central City
Cherokee St
City Park
Community Meeting
Conti
Convention Center Blvd
Curran Blvd
Desire
Desire/Gordon Plaza
East Riverside/Garden District/Irish Channel/St. Thomas
Filmore
Fleur de Lis
Fontainebleau
Fountainebleau
French Quarter
Freret
Gentilly Resilience District
Gentilly Terrace
Gravier St
Green Infrastructure
Hagan Lafitte
Henry Clay
Hollygrove
Hollygrove, Leonidas
Infrastructure Industry Day
Jackson Ave
Joe Brown Park Bridge
Lacour Monique and Eton St.
Lafitte Corridor Greenway
LAKE TERRACE AND OAKS
Lake Vista
Lakeshore
Lakeview
Lakewood
Little Woods
Lower Ninth Ward
Magazine
Magnolia Bridge
Maintenance Improvements
Marconi
Marleyville-Fontainebleau
Maurepas St and Mystery St
Max Pave II
Message from the Mayor
Michoud Blvd
Mid City
Milneburg
Mirabeau Water Garden
Moving New Orleans Bikes
Navarre
New Aurora
New Orleans East
North Claiborne
Oak Park
Octavia Street
Old Spanish Trail
Pilotland
Pines Village
Pittari St.
Plum Orchard / West Lake Forest
Pontchartrain Park
Pontilly
Read Blvd
Resilience
S Galvez
Safe Routes to School
Saratoga Square
St Claude
St Louis Canal
St. Ann
St. Bernard
St. Charles
St. Roch
Streetscape
SWB
Taft Place
Traffic Advisory
Treme-Lafitte
Viavant-Lake Catherine
Village de L’Est
West Bank
West End
Wisner Bridge
Wright Rd
Youth Study Streets


Looking for work?

The City of New Orleans and the Sewerage & Water Board are hiring.

Find jobs with the City

Find jobs with S&WB

Connect to First Source


Contact us

You can contact us directly at roadwork@nola.gov
or by phone at (504) 658-ROAD (7623).