The St. Charles Avenue (Louisiana Avenue to Napoleon Avenue) Resurfacing project, a joint effort between the City of New Orleans and the Louisiana Department of Transportation, is in the final stages, pending completion of asphalt and striping.
Crews recently detoured both the westbound and eastbound lanes in order to complete a large percentage of the remaining asphalt work. Work on this project is expected to wrap up by December 30, weather permitting.
This $1.3M project, designed by Linfield, Hunter, and Junius, LLC., includes the following scope of work:
- Repaving the asphalt roadway from curb-to-curb;
- Installing Americans with Disabilities Act (ADA)-compliant curb ramps at intersections;
- Repairing damaged sidewalks adjacent to ADA ramps;
- Patching in preparation for the next phase of construction; and
- Replacing street tiles.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).