Roadway restoration is ongoing along Dwyer, Bergerac, Savoie and Lourdes streets, and new sidewalk and driveway apron installations are underway throughout the $7.3M Village De L’Est Group B infrastructure improvement project in New Orleans East. Learn more about the project by viewing a copy of the public meeting presentation here.
Construction started in March 2020 and is expected to be complete in spring 2021, weather permitting. The scope of work varies by block but includes:
- Repaving the asphalt and concrete roadway from curb-to-curb in some areas;
- Patching the roadway with asphalt in some areas;
- Repairing some damaged sidewalks and driveway aprons;
- Installing American with Disability Act-compliant curb ramp at intersections; and
- Replacing/repairing damaged underground water lines.