The $3.2M Pines Village Group B project is nearing completion. Pavement restoration work is more than 95 percent complete with crews finishing up sidewalks and driveway aprons. Site-wide clean-up has begun and the construction team is developing a punch list of final items to be addressed. The project is expected to be substantially complete next month.
The scope of work for the project included replacing damaged underground drainage lines, repaving the roadway, replacing damaged sidewalks and driveway aprons, and installing Americans with Disability Act-compliant curb ramps at intersections. Construction began in March 2020.
For access to the presentation that was offered at the March 12, 2020, public meeting click here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).