Beverly Construction crews completed roadway operations that included waterline installation and tie-in on Hauck Drive (Prentiss Avenue to Chef Menteur Highway) on the Read Boulevard Group D project. Tie-in operations for the newly installed waterlines are currently underway. Residents will continue to be notified of work that will impact their access and/or cause disruption to their utilities.
The scope of this $3.3M Patch, Mill, Overlay and Incidental Road Repair project, designed by EJES Incorporated, varies by block but includes:
- Repaving the asphalt roadway from curb-to-curb;
- Patching the roadway with asphalt or concrete;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersection; and
- Replacing / repairing damaged underground water, sewer, and/or drainage lines.
Details of this project were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).