Palmisano Construction in collaberation with Sewerage and Water Board New Orleans (SWBNO), continued waterline tie-ins on the Read East Boulevard Group C project. Crews are also working to complete all water-line point repairs.
Residents will continue to be notified of work that will impact their access and/or cause disruption to their utilities.
The scope of this $3.2M Patch, Mill, Overlay and Incidental Road Repair project varies by block but includes:
- Repaving the asphalt roadway from curb-to-curb;
- Patching the roadway with asphalt or concrete;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersection; and
- Replacing / repairing damaged underground water, sewer, and/or drainage lines.
Details of this project were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.