The $7.3M St. Claude Group C project broke ground in March 2020 and continues to progress on schedule. This full-depth reconstruction project was designed by Rahman & Associates Inc. and is being constructed by Durr Heavy Construction LLC. Click here to view a map of the planned work.
Montegut Street continues to be the main focus of work for Durr Heavy Construction as the street and underground is entirely reconstructed. The contractor will move on to improve other roadways in the project in fall 2020. The project’s scope of work varies by block but includes the following types of work:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
The City of New Orleans hosted a virtual community meeting via Webex in April 2020 to discuss anticipated impacts to the community. View a copy of the presentation here. To be added to the project contact list and track our progress, visit roadwork.nola.gov.