Wallace C Drennan crews continue work on the Pines Village Group A project. Waterline installations are now 60 percent complete, sewer line work is 90 percent complete and planned repaving work is now 50 percent complete. The overall scope of the project also includes repairing damaged sidewalks and driveway aprons; and installing Americans with Disabilities Act-compliant curb ramps at intersections.
The approximately $12.7M project was designed by All South Consulting Engineers Inc., and is estimated to be complete in the fall of 2022, weather permitting.
Access the presentation from the public pre-construction meeting here.