Due to weather delays and necessary repairs to the sewer and drainage system, the completion date for the $1.8M S. Johnson and Melodia Ct. full-depth reconstruction project is now August 1, 2017 – barring additional weather related delays.
Roubion Roads & Streets LLC has completed sidewalk and driveway work throughout much of the project, as well as substantial work on the Nashville Ave. underground utilities. Currently, crews are working on the following tasks:
- Water tie-ins (5) between Nashville Ave. and Octavia St.;
- Testing and approval of all sewer lines followed by:
- Removal of catch basins on Octavia St.;
- Replacement of manholes and catch basins throughout project;
- Final chlorination testing;
- Concrete pouring; and
- Asphalt placing.
This $1.8M City Bond funded project was designed by Lambert Consultants and is being constructed by Roubion Roads & Streets, LLC.