The $4.4M Filmore South Group A project was designed by Volkert, Inc. and is being constructed by Hard Rock Construction, LLC. The project is currently at over 50% complete and construction continues to progress ahead of schedule.
Roadwork is currently focused on the following streets: Miles, King, Moore, Overton, Mandolin, Hamburg, and Cartier. Construction work also includes significant waterline tie-ins in concert with Sewerage & Water Board of New Orleans. The scope of work for the project as a whole varies by block but includes the following types of work:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
The City of New Orleans hosted a pre-construction community meeting in August 2019 to discuss anticipated impacts to the community. View a copy of the presentation here. To be added to the project contact list and track our progress, visit roadwork.nola.gov.