The Lakeview North Group A project began on May 12, 2017. Crews have split the significant incidental road repair project into four quadrants:
- Quad 1 – West End to Canal / Robert E. Lee to Filmore
- Quad 2 – Canal to Orleans / Robert E. Lee to Filmore
- Quad 3 – West End to Canal / Filmore to Harrison
- Quad 4 – Canal to Orleans / Filmore to Harrison
Work will take place in the eastern portion of the project (bounded by Robert E. Lee, Orleans, Harrison, and Canal) during the first four months. Work will take place in the western portion of the project (bounded by Robert E Lee, Canal, Harrison, and West End) during the last four months.
This $2.7M FEMA project was designed by Lambert Consultants and is being constructed by Hard Rock Construction LLC. This project will address damaged sidewalks, driveway aprons, and curbs within the public right-of-way.