May 29, 2020 | Category: District D | Tagged as: Lake Vista
The $2.8M Lake Vista Group A project is set to break ground in June 2020. This project was designed by C & S Consultants, Inc., and will be constructed by Roubion Roads and Streets, LLC.
May 29, 2020 | Category: District D | Tagged as: Filmore
The $4.4M Filmore South Group A project continues to progress on schedule. Designed by Volkert Inc., the project is being constructed by Hard Rock Construction, LLC and has reached approximately 65% completion. Click here to view a map of the project scope.
The $4.2M Filmore North Group B project is set to break ground in June 2020. This project was designed by Professional Engineering Consultants (PEC) Corporation and will be constructed by Fleming Construction Company, LLC.
June 2020 is expected to be the final month of construction for the $6.5M Filmore North Group A project. The project team held final walkthroughs for substantial completion in April 2020, with all remaining punch list items and water line work expected to be completed next month.
May 29, 2020 | Category: District D | Tagged as: Canal Blvd
In May, Palmisano construction crews began installing new curb and gutters, marking out driveway aprons and sidewalks on the northbound side of Canal Boulevard between Robert E. Lee Boulevard and Amethyst Street.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at roadwork@nola.gov or by phone at (504) 658-ROAD (7623).