City of New Orleans contractor The Three C's Properties, Inc. completed work within the first phase of the Lakeshore Group A project. The original scope of work in the first phase, bounded by Orleans Avenue and Canal Boulevard, is complete and pending inspection. The second phase, bounded by West End Boulevard and Canal Boulevard will begin in November.
In October, crews completed roadway repairs on Emerald, Gem, Gen. Haig and Turquoise streets. The City is now awaiting approval from FEMA on additional scopes of work that will improve drainage in the area. Crews are currently 60 percent complete.
This $1.1M Incidental Road Repair project includes the following scope of work:
- Patching the roadway with asphalt;
- Replacing damaged portions of concrete with new, level concrete;
- Repairing damaged curbs and gutters;
- Repairing damaged sidewalks and driveway aprons;
- Installing ADA compliant curb ramps at intersection; and
- Replacing/repairing damaged underground water, and drainage lines.
The City hosted a pre-construction public meeting to discuss the project’s construction sequencing and anticipated impacts. View a copy of the public meeting presentation here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).