TKTMJ crews have resumed work on the Breakwater Drive improvement project. Crews are currently preparing for roadway work, parking lot and pier modifications and relocating the cul-de-sac. With the newly added scope, completion is expected in spring 2021.
Residents will continue to be notified of the work schedule as details develop.
This $5M project, designed by All South Engineering, includes the following scope of work:
- Repaving the asphalt roadway;
- Patching the roadway with asphalt or concrete;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections;
- Adding riprap and rehabilitating the Breakwater retaining wall;
- Adding sidewalk along the retaining wall on both the north and west berms;
- Rehabilitating the parking areas along Breakwater Dr.; and
- Rehabilitating the boat launch area and parking lot.
Details of the construction sequencing and timeline were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).