The $3.4M St. Roch South Group B project, which broke ground in September 2020, continues the full-depth reconstruction project that was designed by HNTB Corporation and is being constructed by Durr Heavy Construction, LLC. The current focus on project is on North Dourgenois Street sewer and water line replacements. This area will continue to be under construction for the next few months. Roadway restoration began on Industry Street will continue for the next several weeks. The project is expected to be completed in winter 2022.

Click here to view a map of the project. The scope of work varies by block including the following:
- Full Reconstruction: Repairing sewage, water, and drainage line, rebuild the street entirely, and repair sidewalks and curbs:
The City of New Orleans hosted a virtual meeting via WebEx in August 2020 to discuss anticipated impacts to the community. View a copy of the presentation here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).