The Mid-City Group A project was designed by Infinity Engineering and is being constructed by Hard Rock Construction, LLC. After work started on this project, additional repairs were deemed necessary due to the current state of the pavement or drainage. As a result, the construction timeframe may be extended for at least six months (winter 2021).
Crews are continuing work on Palmyra and Toulouse streets. Residents are asked to be mindful of ‘No Parking’ signs installed prior to roadwork. Vehicles are eligible for towing if not moved within 24 hours once signs are in place.
View a copy of the presentation here. To be added to the project contact list, and to track our progress, visit RoadWork.nola.gov.
The scope for the $6.3M project varies by block, but includes the following types of work:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repairing damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).