Beverly Construction, LLC, began water line repair work on Harrison Avenue as part of the St. Bernard Group A project in September. For this sequence of the project, water line repair will extend from Harrison Ave. to Buchanan St. to Duplessis St., and to the 4200 block of Alfred St. to the dead end of Alfred St.
Residents will continue to be notified of work that will impact their access and/or cause disruption to their utilities.
The scope of this $4.4M Gulf Engineers and Consultants’ (GEC) designed project includes Patch, Mill, Overlay and Incidental Road Repairs. The project varies by block but includes:
- Resurfacing the roadway with asphalt or concrete;
- Repairing damaged curbs;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replacing/repairing damaged underground water and drainage lines; and
- Repairing damaged sidewalks and driveway aprons.
Details of this project were first made available at the pre-construction public meeting held on September 8, 2020. View a copy of the public meeting presentation here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).