Command Construction Industries, LLC crews are 20 percent complete with the Fleur de Lis Dr. Phase III Reconstruction Project between 30th St. and Old Hammond Hwy. in the West End neighborhood.
Water line installation is complete in the northbound travel lane and three construction crews are currently installing a new sewer line in the northbound travel lane. Sewer line work is approximately 40 percent complete. Work on the drainage lines is scheduled to begin once the sewer work is completed.
Construction work is progressing well, though inclement weather added days to the project schedule.
Two-way traffic will remain diverted onto the traditionally southbound travel lane until work in the northbound travel lane is completed.
The $12M project was awarded to Command Construction Industries, LLC.
The scope of work includes:
- Removing and replacing the underground water, sewer and drainage lines;
- Repaving the roadway; and
- Installing new sidewalks and Americans with Disabilities Act-compliant curb ramps at intersections.