Roubion Roads & Streets, LLC has substantially completed the S. Johnson St. and Melodia Ct. Reconstruction Project in the Marlyville-Fontainebleau neighborhood. With street repairs completed and the roadway reopened to vehicular traffic crews focus on seeding and fertilizing the project’s green space. A final inspection is set for early October.
The scope of work includes:
- Installation of new subsurface drainage, sewer, and waterlines;
- Removal of existing roadway and replace with new asphalt roadway including new concrete curb and gutter bottom;
- Replacement / installation of new catch basins;
- Removal and replacement of sidewalks and driveways aprons;
- Installation of Americans with Disabilities Act-compliant curb ramps at intersections; and
- Manhole adjustments.
This $1.8M City Bond funded project was designed by Richard C Lambert Consultants and is being constructed by Roubion Roads & Streets, LLC.