The Mid-City Group A project was designed by Infinity Engineering and is being constructed by Hard Rock Construction, LLC. Work has started on South St. Patrick Street, Cleveland Avenue and Palmyra Street.
View a copy of the presentation here. To be added to the project contact list, and to track our progress, visit RoadWork.nola.gov.
The scope for the $6.3M project varies by block, but includes the following types of work:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repairing damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).