The $9.1M Central City Group A project is scheduled to begin construction in October 2020. The project was designed by C.H. Fenstermaker and Associates, LLC and is being constructed by Barriere Construction Company.
This project is a full-depth reconstruction and the scope of work varies block by block but includes the following:
- Replace damaged underground water, sewer and drainage lines;
- Repave the roadway;
- Replace damaged sidewalks and driveway aprons; and
- Install Americans with Disabilities Act-compliant curb ramps at intersections.
The City of New Orleans hosted a virtual community meeting via WebEx in August 2020 to discuss anticipated impacts to the community. View a copy of the presentation here.
To be added to the project contact list and track our progress, visit roadwork.nola.gov.