Beverly Construction crews continue paving operations on the Read Boulevard Group D project. Completion of paving operations during the month of September moved this project into substantial completion. New water lines, upgraded drainage and roadway paving are expected to be complete this fall.
The scope of this $3.3M Patch, Mill, Overlay and Incidental Road Repair project, designed by EJES Incorporated, varies by block but includes:
- Repaving the asphalt roadway from curb-to-curb;
- Patching the roadway with asphalt or concrete;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replacing / repairing damaged underground water, sewer, and/or drainage lines.
Details of this project were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).