SEWER REPAIRS, PAVEMENT RESTORATION CONTINUE IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

March 2, 2021   |    Category: District A    |   Tagged as: Hollygrove, Leonidas

SEWER REPAIRS, PAVEMENT RESTORATION CONTINUE IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

The Hollygrove, Leonidas Group A project continues to make progress. Additional sewer line issues were identified, and crews began making those repairs in early February. In addition to laying new wearing course (upper layer in the roadway) layers of asphalt throughout the project area, Drennan Construction Industries, LLC completed the intersection work required at Birch and Cambronne streets. Excavation operations continued, along with forming new Americans with Disabilities Act (ADA)-compliant curb ramps at intersections.

MAYOR CANTRELL AND CITY LEADERS BREAKS GROUND ON THE BAYOU ST. JOHN, FAIRGROUNDS, SEVENTH WARD GROUP B PROJECT

January 27, 2021   |    Category: District A, District C, District D    |   Tagged as: Bayou St. John, Fairgrounds, Seventh Ward

MAYOR CANTRELL AND CITY LEADERS BREAKS GROUND ON THE BAYOU ST. JOHN, FAIRGROUNDS, SEVENTH WARD GROUP B PROJECT

On January 21, 2021, Mayor Cantrell alongside District D Councilman Broussett and District C Councilwoman Kristin Palmer visited Bayou St. John, Fairgrounds, Seventh Ward Group B’s LePage Street to break ground on the $23M infrastructure improvement  project. This month, Barriere construction crews began drainage work and are expected to begin test closures in preparation for future water line tie-ins next month. Crews are also working on roadway and sidewalk restoration work.

BROADMOOR GROUP A PROJECT IS UNDERWAY

January 27, 2021   |    Category: District A, District B    |   Tagged as: Broadmoor

BROADMOOR GROUP A PROJECT IS UNDERWAY

Hard Rock Construction Co., LLC crews broke ground on the $13.6M Broadmoor Group A project in December 2020.  This month, in close collaboration with the Sewerage and Water Board of New Orleans, crews began water line test closures throughout the project. These test closures are in preparation for future water line tie-ins. Crews are also working on roadway and sidewalk restoration. The community will continue to be informed ahead of any work that will involve utility disruption and / or impact their parking and access to their streets.  Residents are asked to continue to be mindful of “No Parking” signs installed prior to roadwork. Vehicles are eligible for towing if not moved within 24 hours of signs being placed.

FINAL PAVING BEGINS AT HAGAN LAFITTE PROJECT

January 27, 2021   |    Category: District A    |   Tagged as: Hagan Lafitte

FINAL PAVING BEGINS AT HAGAN LAFITTE PROJECT

Command Construction Industries, LLC crews are wrapping up construction and paving on all major streets that border the Hagan Lafitte Drainage project.

MAYOR CANTRELL KICKS OFF CITY PARK GROUP A PROJECT; CREWS CONTINUE PAVEMENT AND SEWER WORK

January 27, 2021   |    Category: District A    |   Tagged as: City Park

MAYOR CANTRELL KICKS OFF CITY PARK GROUP A PROJECT; CREWS CONTINUE PAVEMENT AND SEWER WORK

On December 29, 2020, Mayor Cantrell and other ciy leaders kicked off the City Park Group A infrastructure improvement project on Dumaine Street. Fleming Construction Co., LLC crews recently completed main sewer line replacements in the 4000 block of Delgado Street. Crews continue to work on main sewer line replacements on the 800 block of Roosevelt Street. New sidewalks have been installed on St. Peters Street, which includes Americans with Disabilities Act-compliant curb ramps at intersections.  At the end of January, crews will start sewer and water line system replacements and full-depth roadway reconstruction on St. John Court.  All residents will continue to be informed ahead of any construction work that will involve utility disruption and / or impact their parking and access to their street and driveways.

Displaying results 76-80 (of 348)
 |<  <  12 - 13 - 14 - 15 - 16 - 17 - 18 - 19 - 20 - 21  >  >| 

Posts by month

November 2023 (1)
October 2023 (0)
April 2023 (1)
October 2022 (1)
August 2022 (2)
July 2022 (1)
December 2021 (1)
November 2021 (57)
October 2021 (1)
September 2021 (2)
August 2021 (3)
July 2021 (2)
June 2021 (56)
May 2021 (3)
April 2021 (5)
March 2021 (64)
February 2021 (55)
January 2021 (57)
December 2020 (55)
November 2020 (53)
October 2020 (52)
September 2020 (44)
August 2020 (40)
July 2020 (38)
June 2020 (38)
May 2020 (34)
April 2020 (30)
March 2020 (29)
February 2020 (30)
January 2020 (23)
November 2019 (24)
October 2019 (21)
September 2019 (22)
August 2019 (18)
July 2019 (18)
June 2019 (23)
May 2019 (23)
April 2019 (23)
March 2019 (23)
February 2019 (27)
January 2019 (27)
December 2018 (26)
November 2018 (26)
October 2018 (26)
September 2018 (27)
August 2018 (27)
July 2018 (26)
June 2018 (29)
May 2018 (21)
April 2018 (20)
March 2018 (18)
February 2018 (20)
January 2018 (20)
November 2017 (17)
October 2017 (15)
September 2017 (14)
August 2017 (13)
July 2017 (18)
June 2017 (16)
May 2017 (14)
April 2017 (15)
March 2017 (17)

Posts by category

Citywide
District A
District B
District C
District D
District E

Posts by project

Algiers
Aubry St
Audubon
Bayou St. John, Fairgrounds, Seventh Ward
Belleville St
Berkeley Dr
bike lanes
Black Pearl
Black Pearl / East Carrollton
Blue & Green Corridors
Bocage
Bourbon
Breakwater Drive
Broad St
Broadmoor
Bullard Ave
Bywater-Marigny
Canal Blvd
Canal St
Central City
Cherokee St
City Park
Community Meeting
Conti
Convention Center Blvd
Curran Blvd
Desire
Desire/Gordon Plaza
East Riverside/Garden District/Irish Channel/St. Thomas
Filmore
Fleur de Lis
Fontainebleau
Fountainebleau
French Quarter
Freret
Gentilly Resilience District
Gentilly Terrace
Gravier St
Green Infrastructure
Hagan Lafitte
Henry Clay
Hollygrove
Hollygrove, Leonidas
Infrastructure Industry Day
Jackson Ave
Joe Brown Park Bridge
Lacour Monique and Eton St.
Lafitte Corridor Greenway
LAKE TERRACE AND OAKS
Lake Vista
Lakeshore
Lakeview
Lakewood
Little Woods
Lower Ninth Ward
Magazine
Magnolia Bridge
Maintenance Improvements
Marconi
Marleyville-Fontainebleau
Maurepas St and Mystery St
Max Pave II
Message from the Mayor
Michoud Blvd
Mid City
Milneburg
Mirabeau Water Garden
Moving New Orleans Bikes
Navarre
New Aurora
New Orleans East
North Claiborne
Oak Park
Octavia Street
Old Spanish Trail
Pilotland
Pines Village
Pittari St.
Plum Orchard / West Lake Forest
Pontchartrain Park
Pontilly
Read Blvd
Resilience
S Galvez
Safe Routes to School
Saratoga Square
St Claude
St Louis Canal
St. Ann
St. Bernard
St. Charles
St. Roch
Streetscape
SWB
Taft Place
Traffic Advisory
Treme-Lafitte
Viavant-Lake Catherine
Village de L’Est
West Bank
West End
Wisner Bridge
Wright Rd
Youth Study Streets


Looking for work?

The City of New Orleans and the Sewerage & Water Board are hiring.

Find jobs with the City

Find jobs with S&WB

Connect to First Source


Contact us

You can contact us directly at roadwork@nola.gov
or by phone at (504) 658-ROAD (7623).