Reconstruction of the Wisner Bridge over I-610 is slightly delayed and the detour remains in effect. Construction of the new $19.5M bridge began in December 2015. It was originally scheduled to be completed this spring; however, during construction, the Department of Transportation and Development (DOTD) determined that the finger joints, which connect sections of the bridge deck together, did not fit properly.