March 15, 2018 | Category: District E | Tagged as: Lower Ninth Ward
The City of New Orleans Department of Sanitation assisted contractor Beverly Construction LLC with removing debris from the Lower Ninth Ward Northeast Group A project in preparation for sidewalk repairs and waterline replacements.
The Department of Public Works’ construction contractor, Fleming Construction Co., LLC, began waterline replacements on the $4.7M Lower Ninth Ward Northwest Group A project last month.
March 15, 2018 | Category: District E | Tagged as: Bullard Ave
The Department of Public Works’ construction contractor, Roubion Roads and Streets, LLC. has substantially completed the Bullard Avenue project between Hayne Boulevard and Chef Menteur Highway.
March 15, 2018 | Category: District E | Tagged as: Curran Blvd
The Department of Public Works’ construction contractor, Barriere Construction, LLC, has substantially completed repaving Curran Boulevard between Crowder Boulevard and Mayo Boulevard.
March 15, 2018 | Category: District E | Tagged as: Read Blvd
Two FEMA-funded construction projects that will improve infrastructure in the New Orleans East are now underway. The Read Boulevard East Group A project is being constructed by Hard Rock Construction, LLC. Crews have placed traffic control safety signage and barrels on site and are now excavating the roadway. View the project map here.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at roadwork@nola.gov or by phone at (504) 658-ROAD (7623).