Palmisano Construction crews are working on the Plum Orchard/West Lake Forest Group B project. Work on this project began this spring with excavating in preparation for waterline and paving operations. Crews are currently working on North and South Coronet, Flake and Bentley streets.
Residents in the area will continue to be notified of work that will impact their access and / or cause disruption to their utilities. RoadworkNOLA will also notify residents in advance of any extended day or weekend work that may be necessary. Any residents that require reasonable accommodations on the site are encouraged to call the Roadwork NOLA hotline.
This $7M full-depth reconstruction project was designed by Hartman Engineering, Inc. The scope of work varies block by block but includes the following:
- Repave the asphalt roadway from curb-to-curb;
- Patch the roadway with asphalt or concrete;
- Repair damaged sidewalks and driveway aprons;
- Install Americans with Disabilities Act-compliant curb ramps at intersection; and
- Replace / repair damaged underground water or drainage lines.
-
The City of New Orleans hosted a virtual community meeting via Webex in January 2020 to discuss anticipated impacts to the community. View a copy of the presentation here.
To be added to the project contact list and track our progress, visit roadwork.nola.gov.