The Lower Ninth Ward South Group A project began in September 2020 with the replacement of water lines on Tennessee Street. During the month of October, Command Construction crews plan to start tying these new lines into the existing water supply.
Residents in the area will be notified of work that will impact their access and/or cause disruption to their utilities. RoadWork NOLA will also notify residents in advance of any extended day or weekend work that may be necessary.
This $7.6M project was designed by IMS Engineers and is being constructed by Command Construction Co, LLC.
This is a Patch, Mill, Overlay with Incidental Road Repairs, and work varies block by block to include:
- Replacing damaged underground water, sewer and drainage lines;
- Repaving the roadway;
- Replacing damaged sidewalks and driveway aprons; and
- Installing Americans with Disabilities Act-compliant curb ramps at intersections.